Demo

Asaluyeh

10,000 m3/day SWRO Desalination Plant, Power Decreasing Substation, Water Distribution Station and Water Management Project

Specifications

Client Pars Special Economic Energy Zone Organization (PSEEZ)
Contract Supply of potable water for the PSEEZ area
Contract type B.O.T. (Build, Operate & Transfer)
Financing bank Export Development Bank of Iran
Contract awarded 2004
Contractual duration to start up 16 months
Actual duration to start up 8 months
Contract period 20 years from start up
Contractual capacity 10,000 m3/day
Final nominal capacity 12,500 m3/day

1. Production process: The source water is taken from beach wells and is then chlorinated and transferred to sand filters by a transfer pipeline. After storage in raw water tanks, it is then pumped to cartridge filters by a pump station and sent towards the SWRO units. Finally, the permeate water is transferred to concrete tanks via a pump station and transfer pipeline for subsequent distribution.

2. Main components: Beach wells, sand filters, cartridge filters, high pressure pumps, pressure vessels and membranes, raw water and permeate storage tanks, instruments and PLC system.

3. Associated companies: the design and equipment are supplied by Linde, Germany in cooperation with B2A, Austria. All other endeavors are carried out by NVCo.

Distribution station construction, operation, and management

Specifications

Client Pars Special Economic Energy Zone Organization (PSEEZ)
Contract (I) Engineering, construction, and start-up of a water distribution station
Contract type (I) Management Contract
Contract awarded (I) March 2005
Completion date (I) June 2005
Contract (II) Distribution and sales of desalinated water through the constructed water distribution station
Contract awarded (II) June 2005
Contract duration (II) 20 years from start up
Distributed water volume 10,000 m3/day
Final nominal distribution capacity 30,000 m3/day

1. Project process: Water supplied by NVCo's SWRO desalination plant, is transferred by a pump station and PE pipeline to two concrete reservoir tanks with capacities of 200 m3 and 2,500 m3. The water is then pumped to the delivery installation. Tankers with various capacities, specifically designed and constructed for potable water transportation, are loaded and dispatched all across the Pars Special Economic Energy Zone. The furthest end users are located some 100 km away from the distribution station. All of the aforementioned operation is automatically monitored and controlled. The sale price for the transported desalinated water is set based on duties ratified by the PSEEZ Board of Directors as well as the distance between the station and the point of delivery.

2. Associated companies: The entirety of the project is carried out by NVCo.

Power Decreasing Substation

Specifications

Client Pars Special Economic Energy Zone Organization (PSEEZ)
Contract Procurement and instalment of a power decreasing substation and emergency stand-by power station
Contract type Management contract
Contract awarded September 2005
Operation Date February 2006

1. Project targets: Supplying the needed electricity (380-400 V) for the desalination plant was initially in the scope of the client, however, the construction of a power decreasing substation (20 kV to 380-400 V) as well as the emergency power station construction and commissioning was later assigned to NVCo by the PSEEZ through a contract.

2. Main components: The substation was constructed as a 3 story building, with four decreasing transformers, each with a power of 1650 kVA, MV cells, LV cells, fire alarm and extinguishing system, and three diesel generators for a total capacity of 3000 kVA with the relevant change-over cells.

  • PMBOK
  • OHSAS-18001
  • M.I.S
  • ISO-9001
  • ISO-14001
  • ISO-10006
  • HSE-MS
  • ISO-10015

طراحی سایت  All rights reserved NVCo 2015.