Chabahar
32,500 m3/day (Phase I and II) SWRO Desalination Plant
Client | Sistan and Baluchestan Province Water and Wastewater Company |
Contract | Supply of potable water to the city of Chabahar |
Contract type | B.O.O.T. for phase I and B.O.O for phase 2 |
Financing bank | Export Development Bank of Iran |
Contract awarded | 2011 |
Duration to start up | 10 months |
Contract period | 10 years form start up |
Contractual capacity | 15,000 m3/day |
Final nominal capacity | 17,500 m3/day |
Contract awarded | 2013 |
Duration to start up | 10 months |
Contract period | 10 years form start up |
Contractual capacity | 15,000 m3/day |
Final nominal capacity | 17,500 m3/day |
1. After the successful construction and operation of Phase I, the contract for the second phase of the desalination plant was won in a separate tender.
2. Phase I process: The feed water is supplied from the Persian Gulf via a direct intake system. After being dosed with a flocculant, it enters into gravity sand filters. The filtrate is stored in a tank, from where it is directed to cartridge filters and the SWRO units via a pumping station. The permeate from the RO units is transferred to a concrete tank by a pump station and transfer pipeline, and subsequently enters the Chabahar and Konarak water distribution network.
3. Main components: Direct intake system and piping, gravity sand filters, filtered water pump station and reservoir tank, chemical dosing unit, cartridge filters, high pressure pumps, pressure vessels and membranes, storage tanks, CIP unit, permeate water pumping station and pipeline.
4. Associated companies: The design and equipment are supplied by Axiom, Austria, and B2A, Austria. All other endeavors are carried out by NVCo.