SWROSWRO desalination plant — Phase I and II
Chabahar
62,500 m³/day (Phase I, II & III) SWRO desalination plant

chabahar (40)
Technical details
Overview
After the successful construction and operation of Phase I, contracts for the second and third phases were won in separate tenders. Feed water is supplied from the Oman Sea via a direct intake system, pretreated through gravity sand filters, then directed to cartridge filters and SWRO units. Permeate enters the Chabahar and Konarak water distribution network.
Main components
Direct intake system and piping, gravity sand filters, filtered water pump station and reservoir tank, chemical dosing unit, cartridge filters, high pressure pumps, pressure vessels and membranes, storage tanks, CIP unit, permeate pumping station and pipeline.
Associated companies
Design and equipment by Axiom (Austria) and B2A (Austria). All other work carried out by NVCo.
Phase I
- Contract awarded
- 2011
- Duration to start up
- 10 months
- Contract period
- 10 years from start up
- Contractual capacity
- 15,000 m³/day
- Final nominal capacity
- 17,500 m³/day
Phase II
- Contract awarded
- 2013
- Duration to start up
- 10 months
- Contract period
- 10 years from start up
- Contractual capacity
- 15,000 m³/day
- Final nominal capacity
- 17,500 m³/day
Phase III
- Contract awarded
- 2022
- Duration to start up
- 24 months
- Contract period
- Up to 2038
- Contractual capacity
- 20,000 m³/day
- Final nominal capacity
- 22,500 m³/day