Bandar Abbas
2,500 m3/day SWRO Desalination Plant: Persian Gulf Mine & Metal Industries Special Economic Zone
Client | Persian Gulf Mine & Metal Industries Special Economic Zone (PGMISEZ) |
Contract | Supply of potable water for the PGMISEZ area |
Contract type | B.O.O. (Build, Operate & Own) |
Financing bank | Export Development Bank of Iran |
Contract awarded | 2005 |
Duration to start up | 8 months |
Contract period | 10 years form start up |
Contractual capacity | 2,500 m3/day |
Final nominal capacity | 4,000 m3/day |
1. Project process: The source water is taken directly from the Persian Gulf. It is then chlorinated and sent to ground filters via a transfer pipeline. The water then proceeds to a storage tank and is pumped to cartridge filters and the SWRO units. The permeate is sent to the zone's water network via a pumping station and transfer pipeline.
2. Main components: Seawater direct intake, transfer pipeline, ground filter, filtered water storage tank, pump station, filter cartridges, high pressure pumps, pressure vessels and membranes, CIP unit, electrical cells and PLC system.
3. Associated companies: The design and equipment are supplied by Uniha, Austria, in conjunction with B2A, Austria. All other endeavors are carried out by NVCo.